As one of the world’s largest orbital motorways, carrying 15% of the UK’s motorway traffic, any maintenance closures of the M25 must be carefully planned to avoid major disruption. As a result, having real-time, easily accessible and accurate data on the structural condition of all bridges and key infrastructure on the motorway is essential. That’s why our structural monitoring technology was recently deployed.
Our solution
Working closely with Octavius Infrastructure, Allan Martin, our Senior Monitoring Engineer, devised a bespoke package of sensors which he personally supervised the installation of. The sensors duly remained in place for an eight-week period, during which time the client was fed continuous live readings.
Allan Martin explained: “The M25-M23 viaduct dates from the mid-1980s and has a series of bearing plates at different levels. These separate the main deck from the abutments and piers, allowing them to move in relation to one another. The five sets of separate monitoring systems were fitted to special steel plates anchored to the bearing shelf and the deck soffit, This allowed us to monitor the movement of the bearings against temperature, to see whether they had seized or were operating sufficiently; with all the data being transmitted wirelessly to a central gateway on site featuring an internal modem. This then wirelessly uploaded to our Insite portal.
“Insite supplies extremely precise measurements of the bridge deck’s thermal movement in real time and crucially showed that while the bearing plates will shortly require replacement, their present performance remains satisfactory. This meant that planned works rather than emergency work could be scheduled – both saving money and helping to reduce disruption for road users. As a specialist in temporary works and monitoring, Mabey Hire is also in a strong position to be able to provide both the necessary jacking and monitoring of the bridge structure during future repairs.”
Get in touch
Octavius Infrastructure’s senior engineer on the project, Said Enany, commented: “We are a preferred framework contractor for Connect Plus, which takes care of the whole M25 network. In this instance, we are the principal contractor responsible for the work being carried out to the Merstham Viaduct.
“While we have worked with Mabey Hire in the past, this is the first time we have made use of the company’s monitoring equipment. We were very happy with the service we received from the technical department and the data supplied by the sensors via Insite confirmed that we did not need to take urgent action regarding replacement of the bearings.”
Project images
Related news and projects
- Project
- Dalmore Mill, Midlothian
Double excavation in new residential area
- Project
- Fiddlers Ferry, Warrington
Environmental monitoring key to iconic power station demolition
- Project
- New Elvet Bridge, Durham
Unique lifting technique helps get crucial city centre transport job underway
Give us a call
For all project specific design and technical enquiries, please contact your local service team.
Send us an email
If you want to talk to us about your project, send us an email and a brief outline of how we can help and we’ll be in touch.
[email protected]
“While we have worked with Mabey Hire in the past, this is the first time we have made use of the company’s monitoring equipment. We were very happy with the service we received from the technical department and the data supplied by the sensors via Insite confirmed that we did not need to take urgent action regarding replacement of the bearings.”