Propping enables new development in city centre’s financial district

Atlantic Square, Glasgow_2

Project Overview

Location
Sector Building
Products

During development works to a Grade I listed building in the heart of Glasgow’s financial district, we used digital technology and our propping system to protect the original façade of the historic building.

The challenge

The construction of a new 284,000 square foot office space in Glasgow’s financial district required our expertise to hold up the historic building’s listed façade. With the busy city centre location, it was essential that any full road closures were avoided.

Working in collaboration with BAM Construct UK for its clients BAM Properties and TCP Developments Limited, we developed a unique temporary propping system to not only retain the historic façade, but which would also allow the main city centre one-way road to remain open and running throughout the project.

City Centre Development

The construction of a new 284,000 sq ft office in Glasgow’s financial district required specialist support to retain the historic listed façade.

Façade Retention Solution

We designed a bespoke temporary propping system to securely support the façade throughout construction.

Keeping the City Moving

Working with BAM Construct UK for BAM Properties and TCP Developments Limited, our solution allowed the main one-way city centre road to remain open, avoiding full closures and minimising disruption.

Our solution

Our Mass 50 propping solution provided transitional support on the building’s outside face as construction was finalised and the permanent supports were put in place over the following year.

We implemented a unique technique, which reduced the width of the propping system and used the weight of the façade to create a “seesaw” arrangement to avoid the need of excessive kentledge, which meant the road could remain open.

View our Propping Range

To aid this bespoke project, we used BIM to create a highly accurate 3D model of the 175-tonne façade retention system. Through this modelling software, we could test in advance how our Mass 50 solution would work, and monitor any potential clashes with the façade so measurements could be tweaked accordingly.

Through the use of BIM, we were able to make virtual site visits using Virtual Reality (VR) to keep the customer up to date on a day-to-day basis.

Get in touch
Contact Phone Number

Give us a call

For all project specific design and technical enquiries, please contact your local service team

Send us an email

If you want to talk to us about your project, send us an email and a brief outline of how we can help and we’ll be in touch

[email protected]

Get updates
on our latest news,
solutions and projects