A £191 million project to ease congestion at a notorious traffic trouble spot on the M1 was delivered on budget and ahead of schedule by Skanska.
Junction 19 of the M1, which is located on the boundary between the counties of Leicestershire and Northamptonshire, is important for north/south and east/west traffic movements across the UK. Over 150,000 vehicles pass through the existing junction daily, which caused congestion and delays, particularly during peak travel periods.
The construction contractor called on a multitude of sub-contractors to apply their expertise. The team at Mabey Hire were among these, and provided vital groundworks support to enable some of this work.
vehicles per day passing through the junction
supported using our groundworks solution
The work to relieve congestion and improve health and safety involved completely redesigning and rebuilding the intersection of the M1 and M6 motorways, and the A14 trunk road. A number of bridges, underpasses and new exit and access slip roads needed to be added. Skanska contacted Mabey Hire to supply two sets of specialist equipment capable of taking high loads over large spans to enable some of this vital work.
The first excavation, where a bridge foundation was due to be built, had to be capable of supporting loads of over 130kN/m.
The second excavation required three-sided support for the side of the M1 while construction work was carried out below and alongside the live motorway.
The first excavation required a frame to support a 7.7m deep sheet-piled cofferdam with very high loads (over 130kN/m) and a plan size of 22.1m x 11.1m. The engineers at Mabey Hire designed a scheme using our Supershaft Plus and Super Shaftbrace frames, supported by our Super Bracing Struts. We supplied this equipment to a tight timeframe so that the customer could successfully shore the excavation in preparation for the bridge foundation.
The second excavation measured 23.3m x 10m x 10m in size and had the added challenge of being next to the busy M1 motorway. Our temporary works engineers designed a solution using Super Shaftbrace frames supported by Super Bracing Struts for bracing and propping the frame.
This was the best possible system to compare with structural steel in price. All equipment was provided with a very short lead time without the need for on-site fabrication, which allowed the on-site team to install it as quickly and efficiently as possible.
Mabey Hire worked with our site team and temporary works department to provide a viable solution which met our design requirements and site constraints. They were able to supply all equipment within a tight timeframe and provided us with technical support during the installation of the systems
Our engineered solutions range from standard designs to major projects, through to emergencies. We can also offer an end-to-end service from design and supply through to installation and removal.