Our projects

Wastewater system gets helping hand at sea

Port Rodie, Stranraer

Stranraer is the second largest town in the rural landscape of Dumfries and Galloway and it sits on the bank of Loch Ryan, a sea loch humming with Scotland’s only natural oyster bed. The wastewater system for Stranraer and the surrounding areas was deemed outdated and in need of replacement.

211

kN/m load

32m

long bracing

8

Super Bracing Struts

Overview

Outdated wastewater system causing water to discharge into Loch Ryan
We designed a frame for a cofferdam located in the sea
Our Customer Product Specialist assisted with the installation of bracing and strut systems

Products used on this project

The challenge

Situated at Port Rodie on the harbour front, the wastewater treatment works (WwTW) for Stranraer is a primary treatment facility with underground settlement tanks and no sludge treatment facilities (processes used to manage and dispose of sewage sludge produced during sewage treatment), which led to water being discharged into Loch Ryan. In one of the final operations of Scottish Water’s project, they were to construct a new pipe to transfer final effluent to the Irish Sea, removing completely the discharge to Loch Ryan.

We were contacted by sub contractors George Leslie and MWH Constructors to design a frame for the cofferdam, located in the sea close to the harbour wall. The frame was required to withstand a customer calculated loading of 211kN/m; this was achieved by using our Supershaft Plus bracing system. Twin level bracing was installed at 32m long by 5200m wide, along with eight Super Bracing Struts.

Our solution

Our Customer Product Specialist worked along with ABCO workforce to assist with the installation. Working day and night to tie in with the tidal flow. An 800 diameter pipe was bored from the harbour out under the railway and then into the cofferdam. The pipe was approx. 1m below the finished level in the cofferdam and it was then turned 45 degrees and out in to the loch.

The contract period experienced some bad weather conditions, causing crews to stand down when it was too dangerous to work. The project was successfully completed on time with the removal of the frames.

Got a similar project coming up? Get in touch today to discuss your requirements >

It looks like you are working with our

So that we can assist you further, could you share a few details and your download will start straight away.