The 90 year old Sutton Weaver Swing Bridge near Frodsham in Cheshire, carries the busy A56 over the Weaver Navigation. Also used by pedestrians, the bridge has shown increasing signs of deterioration over the years and required extensive restoration to enable it to continue to carry the high volume of traffic it receives daily.
year old bridge
tonnes launch weight
working days
The extensive restoration work included the full replacement of the bridge deck and pedestrian walkways, which meant that it would be out of action whilst this work was undertaken. In order for the repairs to be carried out efficiently and with minimal disruption to the busy route, our challenge was to install a temporary bridge alongside the existing structure, allowing traffic to cross without inconvenience to the public.
The main challenge for our team was the installation and subsequent removal of the bridge. The site is bounded by Clifton Road (A557) – a heavily trafficked highway to the north – and a service road to the south, neither of which could be closed. Lifting the bridge into position by crane was not an option, as it was not possible to get a large enough crane onto the site.
Working with May Gurney under their Canal & River Trust Omnibus 3 Framework contract, we supplied and installed a temporary Mabey Universal bridge to carry traffic during the refurbishment and strengthening of the bridge. The temporary bridge had a span of 36m, a 2-lane carriageway for traffic and a cantilever pedestrian foot walk to one side.
The installation challenges meant there was only one option for our team – to launch, keeping the total length of the structure to an absolute minimum, and sequencing the procedure and equipment deliveries to ensure just-in-time delivery without overloading the restricted storage area available.
The total launch weight was 180 tonnes, including 52 tonnes of equipment, which was then removed from site. Our team completed the installation of the MU bridge in 12 working days.
Our engineered solutions range from standard designs to major projects, through to emergencies. We can also offer an end-to-end service from design and supply through to installation and removal.
Due to the poor structural condition of the existing Darley Abbey footbridge, Derby City Council called on us for our temporary bridging and in-house installation expertise to help reconnect the local community.
Find out moreAstonishing 40-metre-long, double-storey temporary bridge constructed for HS2, providing access for heavy construction equipment and earth-moving plant.
Find out moreDuring a major initiative to remove electricity transmission lines impacting some of the most scenic landscapes across Scotland’s National Parks, our temporary bridging solutions played their part in enabling the works.
Find out moreBespoke groundworks support package enables construction of fish pass in major environmental works on River Severn.
Find out moreThe A372 road was damaged due to flooding, leaving villages cut off for two months. Temporary bridges were required to reconnect residents whilst flood prevention works could be undertaken.
Find out morePooley Bridge village was cut in two by extensive flooding, causing considerable disruption to residents and businesses. This led to an urgent need for a temporary bridge during the design stage of a new, permanent structure.
Find out moreLudlow Castle hosts major festivals throughout the year. Ground protection mats are used to preserve the ground offering safe access to vehicles and pedestrians.
Find out moreIt was identified that the railway bridge on Swing Swang Lane in Maidenhead needed strengthening to remove line restrictions on the railway. Due to our experience and expertise in this field, we were quickly engaged as a key delivery partner.
Find out moreDuring the construction of a new wind farm substation near Inverness, a bridge to carry a 197 tonne load was required. We designed and installed the perfect solution.
Find out moreDuring the removal of an old bridge and construction of a new structure as part of the Crossrail project, a temporary bridge needed to be installed within a possession of just four hours to minimise disruption.
Find out moreAs part of the Crossrail project, a new bridge was required to accommodate overhead cables to introduce greener electric trains. Our temporary bridging system supported the existing services during construction.
Find out moreA major refurbishment project at Stanlow Oil Refinery was going ahead with the replacement of the 475 tonne cyclone head at the heart of it. Delivery to site required our versatile BeamBridge system.
Find out moreA three mile section of the A591 in the Lake District was left completely impassable after it collapsed following flooding. A new route was identified which crossed rivers at two points, meaning two temporary bridges were required.
Find out more