Bespoke solution for new petrol filling tank

Morrisons Filling Station, Gloucester

The grocer, Morrisons planned to expand with a new superstore, forecourt and petrol station in Gloucester as part of their UK store roll-out.

We were approached by contractors ISG to advise on the temporary works in a very tightly timed build programme.

27m

x 7m large excavation

3

weeks from design to installation

2

days for whole cofferdam to be struck out

Overview

Large cofferdam for a new Petrol Filling Station
Tight turnaround project – from design to installation within 3 weeks
Supershaft Plus ensured an excavation clear of struts

Products used on this project

The challenge

A very tight deadline from early design to installation within 3 weeks, which involved weekend working to ensure the forecourt ground was ready for tank delivery.

The other challenge was the mudstone ground conditions across a large excavation. We had to come up with a clear opening solution for the tank arrangements for the new forecourt.

Once access and ground conditions had been assessed, a full method statement, risk assessment and temporary works design was agreed between all parties.

Our solution

We supplied a modular groundworks solution that used our sheet piles supported by our Supershaft Plus clear span shoring frames, protected by our ladder access system.

The excavation was constructed to the 27m x 7m dimensions without the need for any internal bracing struts compromising the clear opening dimensions.

By using our sheet piles, the whole cofferdam was struck out in only 2 days. The sheet piles were specially selected to allow rapid installation and removal with minimum deflections and damage. The piling rig was able to handle the piles without the need for banksmen or piling operatives, which reduced the number of people involved and the removal of lifting chains was a key deciding factor in the improved safety plan for ISG.

The use of our modular Supershaft Plus frames allowed the minimum number of delivery lorries to and from site, giving further environmental benefits to the project. Each element of the frame could be simply installed using a traditional excavator, removing the need for crane and piling mat costs. The speed of assembly of the frame allowed excavation of the pit to begin immediately on completion.

To complete the excavation, we supplied the ladder access system on each end of the cofferdam, allowing landing stages with secure gate access systems to give the required 1.0m barrier protection for the pit.

The quick assembly was overseen by one of our engineers, which allowed the installation team and main contractor to address the installation programme from delivery to extraction and identify all the key safety features on site.

Another project delivered on time, another bespoke solution delivered. Customer delighted with the speed of delivery of the project and a solution that reduced the safety risks of having personnel in the excavation unnecessarily.

Got a similar project coming up? Get in touch today to discuss your requirements >

It looks like you are working with our

So that we can assist you further, could you share a few details and your download will start straight away.